4-Mile Replacement Pipeline

Responsiveness. An extremely tight completion timeline was significantly hampered by substantial and consistent rainfall. The survey team worked around the unfavorable field conditions and was able to complete the project on time.

The southeast Texas project initiated by gathering topographic survey data along an existing 8” pipeline. Survey control was established along the route to be used for the preliminary survey, construction staking, and as-built phases. LJA had two field crews assigned on-site for the duration of the project who kept track of the pipe tally and followed three trench crews and two tie-in crews, enabling the team to complete the project on schedule.

For more information regarding this project, please contact Jeremy Russell, RPLS at jrussell@lja.com.